Flooding in Sindh |Arif Ali, White Star
During one of the hearings of the case in January this year, the court was inclined to refer the matter to the National Accountability Bureau (NAB). The irrigation secretary, however, assured the court that an honest officer would investigate and personally scrutinise the process of awarding the disputed contracts. That officer would submit his report within seven days, the secretary further promised. The judge granted this request.
On January 20, 2016, the irrigation department placed some documents before the court. These included show-cause notices to be issued to the then executive engineer of the Khairpur West division, Khan Bahadur Ujjan, and the Executive Engineer Khairpur East division, Ayaz Ahmed, under Section three of the Removal From Services (Special Powers) Sindh Ordinance, 2000.
One of the allegations cited in the notices was that the two officials had made payments to the contractors, without ensuring that the works undertaken were completed. Taking note of the allegations, the Sindh High Court directed the NAB chairman to scrutinise all the irrigation department contracts under the Annual Development Programme 2014-2015 for the Khairpur East and Khairpur West divisions. That scrutiny is still under way and the officials concerned are facing various inquiries and other departmental actions.
Contractors such as Jalbani argue that the court should have extended the NAB scrutiny to all irrigation department projects across Sindh, since (in some instances) money at stake has been much more than that reportedly embezzled in the two divisions in Khairpur. They cite the example of the rehabilitation and lining of Jamrao Canal, in Mirpur Khas, that is to be done at a whopping 9.12 billion rupees.
“Works like rehabilitation and lining are difficult, even impossible, to verify,” says Jalbani. Water can be shown to have washed away stones and earth utilised in such works. Most of these projects are thus only done on paper and the money allocated for them finds its way into the pockets of officers of the concerned irrigation divisions, he alleges.
Even when the jury is out on all this, one thing is already quite wellknown: something is terribly rotten at the irrigation department.
The documents pertaining to the project show that the contract awarding process for the rehabilitation and lining of Jamrao Canal was flawed from the beginning. The SPPRs state that international competitive bidding should be the default method for all contracts with an estimated cost of 10 million dollars or more. In this case, the original cost of the project was 9.12 billion rupees or 90 million dollars — and, yet, no international bids were invited.
The SPPRs also state that the advertisement for such a project should be published in two widely circulated local English-language newspapers and an internationally known website or any widely-circulated international English-language newspaper. The advertisement, however, was only published in local newspapers.
Taking notice of these violations, the SPPRA wrote to Amjad Ahmed Memon, executive engineer at Mirpur Khas division, on May 5, 2015, advising him to invite open international competitive bidding. He, however, did not pay heed to the letter and continued with the bidding process.
In the meanwhile, other discrepancies were creeping into the process.
While the estimated cost of the project in the original advertisement was set at 9.12 billion rupees, the executive engineer changed it to 9.04 billion rupees in the second advertisement – published on June 17, 2015 – meant to invite pre-qualification applications. A corrigendum was published on July 22, 2015, and then a third advertisement was issued a month later — this time without mentioning the estimated cost, the amount for security deposit and the fee for participation in the bidding process.
Jalbani offered the lowest price to undertake all that work, but hestill could not get the contract.
The SPPRA reminded the executive engineer about the violation of procurement rules. This time, too, he ignored the authority’s advice and continued with the bidding process. The contract was finally awarded to M/S Sardar Ashraf D Baloch (Pvt) Ltd on October 10, 2015. Two months later, the firm was asked to start working on the project.
One Ghulam Hussain, in the meantime, moved the Sindh High Court against the contract. He pleaded the executive engineer had misguided SPPRA officials by writing a letter claiming that permission to limit the contract awarding process to Pakistan-only competitive bidding was accorded by the irrigation department’s secretary. “The then Director Nara Canal and Executive Engineer (Chairman Procurement Committee)/secretary/member have fully discussed the matter of approval with the worthy secretary irrigation department and it has been informed by [the] secretary that [the] signature of [the] section officer is valid and the same [was] issued after the approval of [the] competent authority as likewise the permission was also issued for the scheme of Rohri Canal,” read the heavily worded letter written by the executive engineer. The petitioner alleged the letter did not categorically state that the secretary had approved the limiting of the bidding process to national-level contractors only. The matter is pending trial.
During the hearing of Jalbani’s petition at the Sindh High Court last month, he informed the judges that the executive engineer of Saifullah Magsi irrigation division, Muhammad Bux Seeru, had invited bids for rehabilitation, de-silting and stone pitching work of the Saifullah Magsi Branch, an offshoot of the North Western Canal. Jalbani offered the lowest price to undertake all that work, but he still could not get the contract.
On June 16, 2016, Bhai Khan Lakho, superintending engineer of the Saifullah Magsi Branch, gave the court a lengthy explanation on why the contract had not gone to Jalbani. He, however, failed to explain how the contract was then awarded to a contractor who bid to do the same work for almost twice the money that Jalbani had offered in his bid.
Even when the jury is out on all this, one thing is already quite well known: something is terribly rotten at the irrigation department. A senior official of the department agrees the entire process of awarding contracts suffers from serious flaws. A “well-documented chronicle of irregularities and illegalities” is what he calls it.
This article was originally published in the Herald's September 2016 issue under the headline "In hot water". To read more subscribe to the Herald in print.